You are here ›Scope

Scope 2012-2013

Container Handling Sector:
Purchasing(6)Rubber-Tyred Yard Cranes(RTG).
Purchasing (10) Yard Trailer.
Purchasing (2) Reach Stacker.
Re-planning 10th Of Ramadan Container terminal after adding new area of 30000 m2.

Cargo Handling Sector:
Purchasing (2) cranes 30 tons.

Development & upgrading the current main container quay

Starting Dredging at the end of 2012 to deepen berths alongside the quay wall from 14m to 16m. within 30 months from the date of starting dredging in three phases:
Phase I: Will take about 14 months to deepen the Southern area (multi-purpose quay No. 2) with a length of 350 meters.
Phase II: Takes about 8 months to deepen the Northern area (container quay) with a length 350 meters.
Phase III: Takes about 8 months to deepen the middle area of the quay (Multi Purpose No. 1) with a length of 250 meters.